NCEPT Selection Meeting Timeline:

23 April – ERR submission deadline

30 April – HR Staffing Workbook entries completed

5 May – Facility Priority Placement Tool (Weekly Run)

6 May - NCEPT data executed

10 May – HR resume upload begins

14 May – HR resume upload complete

17 May – Manager Ranking List published (Opened)

21 May – Manager Rankings completed (Closed)

25 May – P21 prepares data for NCEPT board

27 May – NCEPT convenes/adjourns
 

Attachments

  • NCEPT 2021 Q2_Redacted.pdf
    527.3 KB · Views: 347
Last edited by a moderator:
Next NCEPT May 27th, 2021!

View attachment 6039

NCEPT Selection Meeting Timeline:

23 April – ERR submission deadline

30 April – HR Staffing Workbook entries completed

5 May – Facility Priority Placement Tool (Weekly Run)

6 May - NCEPT data executed

10 May – HR resume upload begins

14 May – HR resume upload complete

17 May – Manager Ranking List published (Opened)

21 May – Manager Rankings completed (Closed)

25 May – P21 prepares data for NCEPT board

27 May – NCEPT convenes/adjourns
Fun... Nice name change btw XD
 
Hunger Games Student GIF
 
Next NCEPT May 27th, 2021!

View attachment 6039

NCEPT Selection Meeting Timeline:

23 April – ERR submission deadline

30 April – HR Staffing Workbook entries completed

5 May – Facility Priority Placement Tool (Weekly Run)

6 May - NCEPT data executed

10 May – HR resume upload begins

14 May – HR resume upload complete

17 May – Manager Ranking List published (Opened)

21 May – Manager Rankings completed (Closed)

25 May – P21 prepares data for NCEPT board

27 May – NCEPT convenes/adjourns
This timeline has been removed from KSN. Official dates soon
 
Next NCEPT May 27th, 2021!

View attachment 6039

NCEPT Selection Meeting Timeline:

23 April – ERR submission deadline

30 April – HR Staffing Workbook entries completed

5 May – Facility Priority Placement Tool (Weekly Run)

6 May - NCEPT data executed

10 May – HR resume upload begins

14 May – HR resume upload complete

17 May – Manager Ranking List published (Opened)

21 May – Manager Rankings completed (Closed)

25 May – P21 prepares data for NCEPT board

27 May – NCEPT convenes/adjourns