the next NCEPT will be held on August 23 per the KSN. The August PPT is scheduled to be released on July 27.
August NCEPT temporary modifications
Facilities are either designated as “gaining” or “releasing” facilities for each round.
Round 1
• Releasing facility must be at or above 85% current % CPC to Target (column L of the PPT) and at or above 85% Projected % to Target (column AA of the PPT)
• Releases stop when the facility drops below 85% Current or Projected % to Target
• Gaining facility must be below the Projected National Average (top of column AA of the
PPT)*
• The order of gaining facilities will be based on the most recent decision lens agreement**
• Selections for a single facility will not exceed ten (10) during this panel
Round 2
• Releasing facility must be an ATC-4 through ATC-7 that is currently at or above 90% Current % CPC to Target and at or above 100% Projected % to Target
• Releases stop when the facility drops below 90% Current or 100% Projected % to Target
• Gaining facilities will be considered only from the ATC-8/9s and may be filled until
selection reach a Projected % to Target of 100%
• The order of gaining facilities will be based on the most recent decision lens agreement**
• Gaining facility Trainee to Total Controller ratio is less than 30%
The panel reserves the right to address extraordinary circumstances on an as needed basis. *Projected National Average percentage will be published in the PPT on 08/03/2022
**Decision lens is part of NCEPT data execution on 08/04/2022 Releases
NCEPT Timeline
• Monday, 25 July – ERR submission deadline
• Friday, 29 July – Final day for Facilities to update staffing in SWB
• Tuesday, 2 August – HR Staffing Workbook entries completed
• Wednesday, 3 August – Facility Priority Placement Tool
• Thursday, 4 August – NCEPT data executed
• Monday, 8 August – HR resume upload begins
• Friday, 12 August – HR resume upload complete
• Monday, 15 August – Manager Ranking List published (Opened)
• Friday, 19 August – Manager Rankings completed (Closed)
• Monday, 22 August – P21 prepares data for NCEPT board
• Tuesday, 23 August – NCEPT convenes/adjourns
Category 1: Release dates shall be within three (3) months of selection, or at the election of the employee no later than six (6) months.
Category 2: Release dates shall be within twelve (12) months of selection.
Post NCEPT Selection Meeting Timeline
4th Quarter (August) NCEPT Selection Dates:
• NCEPT meeting adjourns August 23rd
TOL sent to employees no later than September 7, 2022 (two weeks)
• Clock starts August 24, 2022
Category 1 Three month release date
• November 21, 2022 PP25
Category 2 One Year Release Date
• August 28, 2023 PP18
August NCEPT temporary modifications
Facilities are either designated as “gaining” or “releasing” facilities for each round.
Round 1
• Releasing facility must be at or above 85% current % CPC to Target (column L of the PPT) and at or above 85% Projected % to Target (column AA of the PPT)
• Releases stop when the facility drops below 85% Current or Projected % to Target
• Gaining facility must be below the Projected National Average (top of column AA of the
PPT)*
• The order of gaining facilities will be based on the most recent decision lens agreement**
• Selections for a single facility will not exceed ten (10) during this panel
Round 2
• Releasing facility must be an ATC-4 through ATC-7 that is currently at or above 90% Current % CPC to Target and at or above 100% Projected % to Target
• Releases stop when the facility drops below 90% Current or 100% Projected % to Target
• Gaining facilities will be considered only from the ATC-8/9s and may be filled until
selection reach a Projected % to Target of 100%
• The order of gaining facilities will be based on the most recent decision lens agreement**
• Gaining facility Trainee to Total Controller ratio is less than 30%
The panel reserves the right to address extraordinary circumstances on an as needed basis. *Projected National Average percentage will be published in the PPT on 08/03/2022
**Decision lens is part of NCEPT data execution on 08/04/2022 Releases
NCEPT Timeline
• Monday, 25 July – ERR submission deadline
• Friday, 29 July – Final day for Facilities to update staffing in SWB
• Tuesday, 2 August – HR Staffing Workbook entries completed
• Wednesday, 3 August – Facility Priority Placement Tool
• Thursday, 4 August – NCEPT data executed
• Monday, 8 August – HR resume upload begins
• Friday, 12 August – HR resume upload complete
• Monday, 15 August – Manager Ranking List published (Opened)
• Friday, 19 August – Manager Rankings completed (Closed)
• Monday, 22 August – P21 prepares data for NCEPT board
• Tuesday, 23 August – NCEPT convenes/adjourns
Category 1: Release dates shall be within three (3) months of selection, or at the election of the employee no later than six (6) months.
Category 2: Release dates shall be within twelve (12) months of selection.
Post NCEPT Selection Meeting Timeline
4th Quarter (August) NCEPT Selection Dates:
• NCEPT meeting adjourns August 23rd
TOL sent to employees no later than September 7, 2022 (two weeks)
• Clock starts August 24, 2022
Category 1 Three month release date
• November 21, 2022 PP25
Category 2 One Year Release Date
• August 28, 2023 PP18
Last edited by a moderator: