Next NCEPT date isn't worked out yet, but it's expected to be in July.
Telecon said that since we continuing to select controllers for other jobs, we've been continuing the deviation process each month, it's the right thing to do continue NCEPT.
UPDATED:
July 21, 2020 NCEPT Timeline and Changes
The Parties at the national level have agreed to conduct an NCEPT using the following timeline and temporary modifications:
23 June: ERR submission deadline
26 June: Employees certifications entries completed in Staffing Workbook
29 June: HR Staffing Workbook entries completed
29 June: Facility Priority Placement Tool
1 July: NCEPT data executed
2 July: HR resume upload begins
8 July: HR resume upload complete
9 July: Manager Ranking List published (Opened)
14 July: Manager Rankings completed (Closed)
17 July: P21 prepares data for NCEPT board
21 July: NCEPT convenes/adjourns
July 2020 Temporary NCEPT Changes:
Telecon said that since we continuing to select controllers for other jobs, we've been continuing the deviation process each month, it's the right thing to do continue NCEPT.
UPDATED:
July 21, 2020 NCEPT Timeline and Changes
The Parties at the national level have agreed to conduct an NCEPT using the following timeline and temporary modifications:
23 June: ERR submission deadline
26 June: Employees certifications entries completed in Staffing Workbook
29 June: HR Staffing Workbook entries completed
29 June: Facility Priority Placement Tool
1 July: NCEPT data executed
2 July: HR resume upload begins
8 July: HR resume upload complete
9 July: Manager Ranking List published (Opened)
14 July: Manager Rankings completed (Closed)
17 July: P21 prepares data for NCEPT board
21 July: NCEPT convenes/adjourns
July 2020 Temporary NCEPT Changes:
- Amend ERR MOU Section 12 A, Category 1 as follows: Category 1 (Green): CPC Current and Projected AOB > 90% Facility CPC staffing level: Release dates shall be within twelve (12) months of selection.
- Amend ERR MOU Section 12 A, Category 2 as follows: Category 2 (Green): CPC Current and Projected AOB >85%: Release dates shall be within twelve (12) months of selection.
- Add the following to NCEPT SOP paragraph 3.5.5:: 3.5.5. A facility will normally not be considered eligible to receive employees if the ratio of CPC-IT/DEV to total number of controllers is at or above 30%.